July 9, 2021

  • Photo 1: work begins on the roof to apply seismic upgrades and eventual reroofing.

    roofing work

    Photos 2 and 3: the elevator shaft continues to be constructed. Removal of the concrete floor in this section has exposed the basement area underneath.

    working on elevator shaft

    exposed basement area

    Photo 4: shoring supports the roof over the gym area.

    shoring supports in place

    Photo 5: a new vestibule is being framed at the main entrance to the building. Additional security will help monitor access.

    framing for entry vestibule

    Comments (-1)

July 2, 2021

  • Photos 1 and 2: with the concrete floor removed, the level underneath is exposed and work can begin on the elevator shaft. .

    elevator shaft under construction

    exposed level under cut floor

    Photo 3: walls in the school hallway are exposed in preparation for seismic upgrades.

    exposed hallway walls

June 23, 2021

  • Photos 1 and 2: saw-cutting has started to break up part of the concrete floor above the lower level to create an elevator shaft for ADA access.

    concrete saw-cutting operation

    saw-cut pieces of stairway

    Photo 3: an electrical panel and associated wiring will be removed on the lower level to make way for the elevator door.

    removing electrical wiring

    Photos 4 and 5: select walls are being exposed to allow access for seismic upgrade work.

    crew members review work for walls

    exposed classroom wall

Milestones