Photo 1: fencing mesh and lockable gates have been added at the side entrance and fire lane.
Photo 2: the fencing continues along the perimeter of the play field area to enclose it and securely separate it from the parking lot.
Photo 3: a gate at the southeast edge of the play field will have locking hardware added to prevent entry during school hours.
Nov. 23, 2022
Photos 1 and 2: posts have been installed to add fencing along the perimeter of the play field to separate students from the parking lot and better secure the campus.
Photo 3: fencing fabric has been added to the new fence at the front of the school.
Nov. 11, 2022
Photos 1 and 2: additional fencing is being installed along the perimeter of the south front of the campus to further secure this side.
Aug. 9, 2022
Photos 1 and 2: security hardware installation and wiring for the new vestibule doorway have been completed. The doors and card entry access have been tested and are fully operational.
Aug. 2, 2022
Photos 1 and 2: the new vestibule doorway is nearly complete. Once the card access reader and other security wiring are finished, the doorway will provide an extra barrier against unauthorized persons.
July 26, 2022
Photos 1 and 2: frames have been installed for the new vestibule doorway.
July 19, 2022
Photos 1 and 2: a crew member prepares for painting of the vestibule doorway, laying down protective tarp and taping around the edges.
July 12, 2022
Photos 1 and 2: sheetrock has been added over the framing for the new vestibule doorway. Security pathways are being installed for hooking up the new doors.
June 28, 2022
Photo 1: the front entry is closed while the entry vestibule is renovated to upgrade security and limit entry into the rest of the building.
Photos 2-3: framing for the second set of doors in the vestibule has been constructed.