• Bond construction timeline - Ladd Acres

     


Scope of Work

  • Please note that project costs and schedules may fluctuate due to cost of materials and labor, conditions at the site, unforeseen and/or revised scope, and other factors. Projected budget: $9.9 million

    Summer 2019

    • Flexible Furniture

    In summer 2019, Ladd Acres classrooms will receive new flexible furniture (FFE) that promotes engagement and learning. Work will also begin on replacing the domestic water piping.

    Summer 2020

    • Improvements, New Gym, Playground

    Ladd Acres will undergo major renovations in summer 2020 with the construction of safety and seismic upgrades and the addition of air conditioning. A new, dedicated gymnasium for PE and activities - separate from the cafeteria - and an upgraded, ADA-accessible playground will be exciting additions for the Ladd community.

    Completed Projects

    • Parent/Bus Dropoff

    Ladd Acres' parking lots and parent/bus dropoffs were completely remodeled in summer 2018. The traffic pattern of the new dropoff areas will separate personal vehicles from the buses, not only enhancing pedestrian and driver safety, but allowing for a smoother flow of traffic during dropoff and pickup times.

    • Fencing

    New fencing and gates were installed in summer 2018 to enclose the perimeter of the school building for additional safety and security.

  • Project Managers

    Hillsboro School District

    • Water pipe replacement: Jim Peterson

    Cornerstone Management Group

    • Parent/bus dropoff: Todd Johnson
    • Fencing: Luke Harkness

    Architect/Engineer

    • Parent/bus dropoff: 3J Consulting

    Contractors

    • Parent/bus dropoff: Kerr Contractors
    • Fencing: Town & Country Fence Co. of Oregon